Carrying energy safely from the source to the point of consumption requires a soundly engineered network infrastructure. Our overhead and underground power network service covers the construction of MV and LV power transmission lines, underground cable networks, and grid connection facilities. We carry out both new construction and renewal of existing networks for industrial facilities, organized industrial zones, mass housing projects, and infrastructure investments.
Miratek takes on network works on a turnkey basis, from route survey to energization. All official steps — including distribution company approvals, design ratification, and provisional acceptance — are followed up as a single point of contact. Our field teams consist of EKAT-certified personnel, and all work is carried out in accordance with the applicable regulations and specifications.
The choice between an overhead line and an underground cable solution is made through an engineering assessment based on route conditions, cost, and operational safety criteria, and we offer full execution capability for both types of installation.
Network Installation Technical Summary
| Voltage level | LV (0.4 kV) and MV (1-35 kV) |
| Installation type | Overhead power transmission line, underground cable network, mixed route |
| Application area | Industrial facilities, OIZ infrastructure, residential districts, public projects |
| Works covered | Pole installation, conductor stringing, cable ducting, joint and termination installation |
| Approval processes | Including distribution company design ratification and acceptance procedures |
| Delivery model | Turnkey, single point of contact |
How We Work
Route Survey
The line route is examined on site; ground conditions, existing infrastructure, and right-of-way permits are assessed.
Design and Approval
The network design is prepared, and design ratification is obtained from the relevant distribution company and authorities.
Material Procurement
Poles, conductors, cables, and accessories are procured from approved brands in accordance with the specification.
Site Works
Pole erection, conductor stringing, or excavation and cable laying are carried out under occupational safety procedures.
Testing and Energization
Cable tests and line checks are completed, and energization is performed under the supervision of the distribution company.
Acceptance and Handover
Provisional acceptance procedures are followed up, and handover is completed with as-built drawings and test reports.
Scope of Work
- MV and LV overhead line construction, pole erection, and conductor stringing
- Underground cable trench excavation, duct and manhole construction
- MV and LV underground cable laying, joint and cable termination installation
- Construction of network connection and sectionalizing points
- Renewal and relocation of existing networks
- Management of distribution company approval, ratification, and acceptance processes
Frequently Asked Questions
Should we choose an overhead line or an underground cable?
The choice depends on route conditions. Underground cable offers advantages in safety and appearance within urban and on-site areas, while an overhead line is usually the more economical solution over long distances. After the site survey, both options are presented comparatively with cost and operational criteria.
Who follows up the distribution company approval processes?
All official processes — including design ratification, site supervision, and acceptance — are handled by Miratek. Our client works with a single point of contact and carries no burden of inter-agency correspondence.
Our existing power transmission line requires a route change — is this within scope?
Yes, relocation of existing lines is part of the service. The new route is designed, the necessary permits are obtained, and the changeover is planned to keep the power outage as short as possible.